[?] A summary of the violations found during the inspection are listed below.

No critical violations were documented at the time of inspection.

No violations were documented at the time of inspection.


Inspection Information


Facility Type: Commercial FSO < 25000 sq. ft.

[?] Inspection Type: Consultation

Inspection Date: 21-September-2016


Comments
In order Health Department approval to re-open the Food Service Operation (FSO) the following must be completed:
1) Caulk along all wall and counter top junctures around the Customer Drink bar and beverage area by drive-thru window and around the new food preparation sink
2) Separate the drains from the over flow drain and the Ice bin at the Drink Bar
3) Provide documentation that a licensed Pest Control Operator was hired to help with the flying insect issue
4) Cornellis CB3023-AV and ED300-BCZ are both new beverage dispensing equipment installed
5) Seal all holes in the FRP wall material throughout the facility
6) Provide Soap, a means to dry hands, Employees Must Wash Hands signage and trash can with lid (Women's Restroom) at all hand washing sinks
7) Ensure that Ventilation (exhaust) is installed in both rest-rooms
8) Seal the hole in the wall between the walk-in freezer and cooler where the condensate drain has been installed. Ice accumulation has already occurred in the freezer.
9) Provide a Air Gap (1 to 2 inches) on the condensation drain from the walk-in units
10) New hot water tank has been installed with 75,600 BTU's with a 72.82 gall recovery which meets the minimal spec according to the FDA requirements
11) Re-caulk around the mop sink
12) Replace the Mop Sink Faucet fixture or provide backflow prevention device on hose and water source
13) Separate the drainage from the ice maker and the ice bin - both are required to be air gapped with an indirect connection
14) Provide backflow prevention devices on all equipment water lines (Ice machine, ice machine, beverage dispensing equipment if not already provided, etc.)
15) Provide documentation from final building and fire departments approving the occupancy of the facility
16) All cold holding equipment shall be functioning properly and supplied with the proper temperature measuring devices in the correct locations
17) Provide access to the location of the grease interceptor or have knowledge of where the location is and the last time if was serviced

This list is contingent upon additional review of the facility.
Follow-up inspection has been scheduled for Friday 9/23/2016 at 12:30 PM.