[?] A summary of the violations found during the inspection are listed below.

3701-31-04 ( D )(6)(a) / ORP reading shall be 650 millivolts or greater.
ORP reading was below 650 mv. The ORP reading was 565. Note: Make proper adjustments.
Have the ACC unit inspected to determined why the ORP is low. Correct By: 06-Jul-2021
3701-31-04 (B)(6)(f) / Required turnover rates are sufficient
Required turnover rates were not met. The turnover rate was only 70 gpm. The rate should be a minimum of 79 gpm.
Have the circulation system evaluated to determine why the turnover rates are not able to be met. Once the reasons have been determined have the issue repaired. If necessary, submit plans to the Ohio Department of Health to review and approve. Correct By: 06-Jul-2021


Inspection Information


Facility Type: Pool

[?] Inspection Type: Standard

Inspection Date: 30-June-2021

Comments
Ensure the noted findings are corrected before next routine inspection. Otherwise, all other water parameters met requirements and paperwork was filled out and recorded correctly. Good job.